Introduction
In
my opinion, one of the most difficult and critical activities in IT is the
estimation process. I believe that it occurs because when we say that one
project will be accomplished in such time by at such cost, it must happen.
If
it does not happen, several things may follow: from peers' comments and senior
management's warnings to being fired depending on the reasons and seriousness
of the failure.
Before even thinking of moving to Systems test at my organization, I always heard from the development group members that the estimations made by the Systems test group were too long and expensive. Then, when I arrived at my new seat, I tried to understand the testing estimation process.
The testing estimation process in place was quite simple. The inputs for the process, provided by the development team, were: the size of the development team and the number of working days needed for building a solution before starting systems tests.
The testing estimation process said that the number of testing engineers would be half of the number of development engineers and one third of the number of development working days.
Before even thinking of moving to Systems test at my organization, I always heard from the development group members that the estimations made by the Systems test group were too long and expensive. Then, when I arrived at my new seat, I tried to understand the testing estimation process.
The testing estimation process in place was quite simple. The inputs for the process, provided by the development team, were: the size of the development team and the number of working days needed for building a solution before starting systems tests.
The testing estimation process said that the number of testing engineers would be half of the number of development engineers and one third of the number of development working days.
A
spreadsheet was created in order to find out the estimation and calculate the
duration of tests and testing costs. They are based on the following formulas:
Testing working days = (Development working days) / 3.
Testing engineers = (Development engineers) / 2.
Testing costs = Testing working days * Testing engineers * person daily costs.
As the process was only playing with numbers, it was not necessary to register anywhere how the estimation was obtained.
To exemplify how the process worked, if one development team said that to deliver a solution for systems testing it would need 4 engineers and 66 working days then, the systems test would need 2 engineers (half) and 21 working days (one third). So, the solution would be ready for delivery to the customer after 87 (66+21) working days.
Just to be clear, in testing time, it was not included the time for developing the test cases and preparing the testing environment. Normally, it would need an extra 10 days for the testing team.
Testing working days = (Development working days) / 3.
Testing engineers = (Development engineers) / 2.
Testing costs = Testing working days * Testing engineers * person daily costs.
As the process was only playing with numbers, it was not necessary to register anywhere how the estimation was obtained.
To exemplify how the process worked, if one development team said that to deliver a solution for systems testing it would need 4 engineers and 66 working days then, the systems test would need 2 engineers (half) and 21 working days (one third). So, the solution would be ready for delivery to the customer after 87 (66+21) working days.
Just to be clear, in testing time, it was not included the time for developing the test cases and preparing the testing environment. Normally, it would need an extra 10 days for the testing team.
The Rules
1st Rule: Estimation
shall be always based on the software requirements
All estimation should be based on what would be tested, i.e.,
the software requirements.
Normally,
the software requirements were only established by the development team without
any or just a little participation from the testing team. After the
specification have been established and the project costs and duration have
been estimated, the development team asks how long would take for testing the
solution. The answer should be said almost right away. Then, the software
requirements shall be read and understood by the testing team, too. Without the
testing participation, no serious estimation can be considered.
2nd Rule: Estimation
shall be based on expert judgment
Before
estimating, the testing team classifies the requirements in the following
categories:
" Critical: The development team has little knowledge in how to implement it;
" High: The development team has good knowledge in how to implement it but it is not an easy task;
" Normal: The development team has good knowledge in how to implement.
The experts in each requirement should say how long it would take for testing them. The categories would help the experts in estimating the effort for testing the requirements.
" Critical: The development team has little knowledge in how to implement it;
" High: The development team has good knowledge in how to implement it but it is not an easy task;
" Normal: The development team has good knowledge in how to implement.
The experts in each requirement should say how long it would take for testing them. The categories would help the experts in estimating the effort for testing the requirements.
3rd Rule: Estimation
shall be based on previous projects
All
estimation should be based on previous projects. If a new project has similar
requirements from a previous one, the estimation is based on that project.
4th Rule: Estimation
shall be based on metrics
My
organization has created an OPD, Organization Process Database, where the
project metrics are recorded. We have recorded metrics from three years ago
obtained from dozens of projects.
The number of requirements is the basic information for estimating a testing project. From it, my organization has metrics that guide us to estimate a testing project. The table below shows the metrics used to estimate a testing project. The team size is 01 testing engineer.
Metric Value
1.Number of test cases created for each requirement 4,53
2.Number of test cases developed by Working day 14,47
3.Number of test cases executed by Working day 10,20
4.Number of ARs for test case 0,77
5.Number of ARs verified by Working day 24,64
For instance, if we have a project with 70 functional requirements and a testing team size of 2 engineers, we reach the following estimates:
Metric Value
Number of test cases - based on metric 1 317,10
Preparation phase - based on metric 2 11 working days
Execution phase - based on metric 3 16 working days
Number of ARs - based on metric 4 244 ARs
Regression phase - based on metric 5 6 working days
The testing duration is estimated in 22 (16+6) working days. Plus, 11 working days for preparing it.
The number of requirements is the basic information for estimating a testing project. From it, my organization has metrics that guide us to estimate a testing project. The table below shows the metrics used to estimate a testing project. The team size is 01 testing engineer.
Metric Value
1.Number of test cases created for each requirement 4,53
2.Number of test cases developed by Working day 14,47
3.Number of test cases executed by Working day 10,20
4.Number of ARs for test case 0,77
5.Number of ARs verified by Working day 24,64
For instance, if we have a project with 70 functional requirements and a testing team size of 2 engineers, we reach the following estimates:
Metric Value
Number of test cases - based on metric 1 317,10
Preparation phase - based on metric 2 11 working days
Execution phase - based on metric 3 16 working days
Number of ARs - based on metric 4 244 ARs
Regression phase - based on metric 5 6 working days
The testing duration is estimated in 22 (16+6) working days. Plus, 11 working days for preparing it.
The Rules
5th Rule: Estimation
shall never forget the past
I
have not sent away the past. The testing team continues using the old process
and the spreadsheet. After the estimation is done following the new rules, the
testing team estimates again using the old process in order to compare both
results.
Normally, the results from the new estimate process are cheaper and faster than the old one in about 20 to 25%. If the testing team gets a different percentage, the testing team returns to the process in order to understand if something was missed.
6th Rule: Estimation
shall be recorded
All
decisions should be recorded. It is very important because if requirements
change for any reason, the records would help the testing team to estimate
again. The testing team would not need to return for all steps and take the
same decisions again. Sometimes, it is an opportunity to adjust the estimation
made earlier.
7th
Rule: Estimation shall be supported by tools
A
new spreadsheet has been created containing metrics that help to reach the
estimation quickly. The spreadsheet calculates automatically the costs and
duration for each testing phase.
There is also a letter template that contains some sections such as: cost table, risks, and free notes to be filled out. This letter is sent to the customer. It also shows the different options for testing that can help the customer decides which kind of test he needs.
There is also a letter template that contains some sections such as: cost table, risks, and free notes to be filled out. This letter is sent to the customer. It also shows the different options for testing that can help the customer decides which kind of test he needs.
8th Rule: Estimation shall
always be verified
Finally,
All estimation should be verified. I've created another spreadsheet for
recording the estimations. The estimation is compared to the previous ones
recorded in a spreadsheet to see if they have similar trend. If the estimation
has any deviation from the recorded ones, then a re-estimation should be made.
|
|
|
|
|
|
|
Sl.No
|
Parameters
|
Best Case
|
Worst Case
|
Possible
|
|
1
|
No. Of Test Modules
|
|
|
|
|
2
|
No.of Test Requirements
|
|
|
|
|
3
|
No. of test cases/requirement
|
|
|
|
|
5
|
Total number of test cases
|
|
|
|
|
6
|
% of complex1 test cases *
|
|
|
|
|
6a
|
No.of complex1 test cases
|
|
#VALUE!
|
0
|
|
7
|
% of complex2 test cases *
|
30
|
|
|
|
7a
|
No. of complex 2 test cases
|
7.5
|
0
|
0
|
|
8
|
No. of complex3 test cases *
|
2
|
0
|
0
|
|
9
|
No. of Test analyst
|
3
|
|
|
|
10
|
Test Analyst knowledge
|
|
|
|
|
11
|
No. of test cycles
|
|
|
|
|
12
|
Incident reporting and closing
|
|
|
|
|
13
|
% incident getting fixed
|
|
|
|
|
14
|
Test case overhead time
|
|
|
|
|
15
|
Test Case rework time/ cycle
|
|
|
|
|
16
|
Contigency factor
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Test Case development time
|
|
|
|
|
|
Test Case Execution time
|
|
|
|
|
|
|
|
|
|
|
|
*Complex 1 Weightage
|
2
|
Note: Test cases that need to be
executed for n number of data can be clasified as Complex 1 |
|
|
|
*Complex 2 Weightage
|
1.5
|
|
|
|
|
*Complex 3 weightage
|
1
|
|
|